2007 г. Kamensk Uralsky, Sverdlovsk region
2004-2007 гг.

From 2004 to 2007 UKKSH CJSC performed the following range of works for Kamensk-Uralsky Metallurgical Plant OJSC:

Development and approval of a project to replace the main drive of the hot rolling mill 2840 “QUARTO” in Gosgortekhnadzor and Civil Defense and Emergencies

Design and survey work of the compressor cooling system in workshop No. 41, with technical re-equipment. A set of works on the design and construction of a cold vestibule and a heat-insulated annex of a section of technological equipment building of workshop No. 36

Development and coordination with the Gosgortekhnadzor authorities of the project on commissioning of smelting and foundry units No. 19,20 in workshop No. 36

Design and overhaul of saltpeter and quenching baths in workshop No. 2

Design air-circulation furnace direct electric. heating

Design of steam removal of foundry machines

A set of design work at the facility "Installation of bright annealing furnaces" in workshop No. 2 A set of design work at the facility "Transfer of equipment in workshop No. 3 building 40"